Parish Councillors held a public drop in meeting on Monday 29th July to display the new architects plans and around 15 parishioners attended. There were several small groups engaged in conversation over the new drawings, the broad timeline for next steps and information on the fundraising campaign. The latest drawings are all posted below.
The estimated broad timeline for the project is:
  • Planning application August to December 2024
  • Fundraising ongoing until summer 2025
  • Structural surveys, civil and drainage surveys, construction drawings and specifications January to March 2025
  • Invite construction tenders, review and appoint contractor April to June 2025
  • Construction from 2nd half of 2025
The latest cost estimate is £877,500
Fundraising achieved so far £350,000 made up from:
SDNPA CIL Grant  £100K
Squire Cottages Charity £100K
Public works loan £150K
On going fundraising from other sources such as grant making organisations, to be announced.
We wish to thank those parishioners who attended the meeting. Parish Councillors will be reflecting on feedback and comments received at the meeting, as well as kind offers of help with the project.
The Parish Council will give further project updates when there is news to report…

 

Bury Parish Council
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.